We are excited to share the latest progress on our extensive construction project. The transformation included:
• Clearing and preparation of a previously forested area on over 42 acres of land
• Extensive cut and fill work
• Installation of storm drainage and sanitary sewer systems
• Construction of 22,000 square feet of block retaining walls
• Development of a detention basin and infiltration basin
• Over 100,000 square feet of concrete flatwork completed
• Installation of 40,000 linear feet of curb work
• Paving across 900,000 square feet
Our team remains dedicated to delivering quality and efficiency in every aspect of our projects. Stay tuned for the next one!